4000 Series

Rotation (Rpm)*
Pitch (mm)
Total Stitch Length (cm)(Per Bigbag)**
Operator Efficiency (%)%80***



RESULT
Quantity Per Minute
Quantity Per Hour
Quantity Per Day (8 hours)

(*) The rotation advised for optimum efficiency.
(**) Total stitch length, all the edges to be sewn must be considered (cm).
(***) The average efficiency of an operator with unavoidable time losses ( 80 % is taken as global average ).
Pitch : Distance between the 2 hits of a needle (mm).
Rotation : Total hits of a needle per minute.

SS 3000 Series

Rotation (Rpm)*
Pitch (mm)
Total Stitch Length (cm)(Per Bigbag)**
Operator Efficiency (%)%80***



RESULT
Quantity Per Minute
Quantity Per Hour
Quantity Per Day (8 hours)

(*) The rotation advised for optimum efficiency.
(**) Total stitch length, all the edges to be sewn must be considered (cm).
(***) The average efficiency of an operator with unavoidable time losses ( 80 % is taken as global average ).
Pitch : Distance between the 2 hits of a needle (mm).
Rotation : Total hits of a needle per minute.

3700 Series

Rotation (Rpm)*
Pitch (mm)
Total Stitch Length (cm)(Per Bigbag)**
Operator Efficiency (%)%80***



RESULT
Quantity Per Minute
Quantity Per Hour
Quantity Per Day (8 hours)

(*) The rotation advised for optimum efficiency.
(**) Total stitch length, all the edges to be sewn must be considered (cm).
(***) The average efficiency of an operator with unavoidable time losses ( 80 % is taken as global average ).
Pitch : Distance between the 2 hits of a needle (mm).
Rotation : Total hits of a needle per minute.

3500 Series

Rotation (Rpm)*
Pitch (mm)
Total Stitch Length (cm)(Per Bigbag)**
Operator Efficiency (%)%80***



RESULT
Quantity Per Minute
Quantity Per Hour
Quantity Per Day (8 hours)

(*) The rotation advised for optimum efficiency.
(**) Total stitch length, all the edges to be sewn must be considered (cm).
(***) The average efficiency of an operator with unavoidable time losses ( 80 % is taken as global average ).
Pitch : Distance between the 2 hits of a needle (mm).
Rotation : Total hits of a needle per minute.

3800 Series

Rotation (Rpm)*
Pitch (mm)
Total Stitch Length (cm)(Per Bigbag)**
OOperator Efficiency (%)%80***



RESULT
Quantity Per Minute
Quantity Per Hour
Quantity Per Day (8 hours)

(*) The rotation advised for optimum efficiency.
(**) Total stitch length, all the edges to be sewn must be considered (cm).
(***) The average efficiency of an operator with unavoidable time losses ( 80 % is taken as global average ).
Pitch : Distance between the 2 hits of a needle (mm).
Rotation : Total hits of a needle per minute.

4500 Series

Rotation (Rpm)*
Pitch (mm)
Total Stitch Length (cm)(Per Bigbag)**
Operator Efficiency (%)%80***



RESULT
Quantity Per Minute
Quantity Per Hour
Quantity Per Day (8 hours)

(*) The rotation advised for optimum efficiency.
(**) Total stitch length, all the edges to be sewn must be considered (cm).
(***) The average efficiency of an operator with unavoidable time losses ( 80 % is taken as global average ).
Pitch : Distance between the 2 hits of a needle (mm).
Rotation : Total hits of a needle per minute.

4700 Series

Rotation (Rpm)*
Pitch (mm)
Total Stitch Length (cm)(Per Bigbag)**
Operator Efficiency (%)%80***



RESULT
Quantity Per Minute
Quantity Per Hour
Quantity Per Day (8 hours)

(*) The rotation advised for optimum efficiency.
(**) Total stitch length, all the edges to be sewn must be considered (cm).
(***) The average efficiency of an operator with unavoidable time losses ( 80 % is taken as global average ).
Pitch : Distance between the 2 hits of a needle (mm).
Rotation : Total hits of a needle per minute.